Project Timeline
Phase-by-phase Gantt view with baseline vs actual schedule
Apartemen Grand Cisarua·PT Graha Nusantara Indah·Cisarua, Bogor, Jawa Barat
10
Total Phases
8
Completed
2
In Progress
8
Delayed
Legend Baseline Completed (on time) Completed (delayed) In Progress (on track) In Progress (delayed) Not Started
202520262027 | |||||
|---|---|---|---|---|---|
| Phase | Baseline | Actual | AprJulOctJanAprJulOctJanAprJul | Status | Involved |
Coordination General | 6 Jan 2025 → 31 Jan 2025 | 6 Jan 2025 → 31 Jan 2025 | Completed | Andriani | |
CDA 1 Design | 13 Jan 2025 → 28 Feb 2025 | 13 Jan 2025 → 7 Mar 2025 | Completed | Rina | |
CDA 2 Design | 1 Mar 2025 → 15 Apr 2025 | 10 Mar 2025 → 30 Apr 2025 | Completed | Rina | |
SDA Design | 16 Apr 2025 → 30 Jun 2025 | 5 May 2025 → 20 Jul 2025 | Completed | Rina | |
DD Design | 1 Jul 2025 → 31 Aug 2025 | 21 Jul 2025 → 30 Sep 2025 | Completed | Rina | |
CD Design | 1 Sep 2025 → 31 Oct 2025 | 1 Oct 2025 → 30 Nov 2025 | Completed | Rina | |
Tender Procurement | 1 Nov 2025 → 15 Dec 2025 | 1 Dec 2025 → 20 Jan 2026 | Completed | — | |
Shop Drawing Review Construction | 16 Dec 2025 → 28 Feb 2026 | 21 Jan 2026 → 31 Mar 2026 | Completed | — | |
Site Visit Construction | 1 Jan 2026 → 30 Jun 2027 | 1 Feb 2026 → ongoing | In Progress | — | |
CA Construction | 1 Feb 2026 → 1 Mar 2026 | 15 Feb 2026 → ongoing | Delayed | Rina | |