Project Timeline

Phase-by-phase Gantt view with baseline vs actual schedule

Apartemen Grand Cisarua·PT Graha Nusantara Indah·Cisarua, Bogor, Jawa Barat
10
Total Phases
8
Completed
2
In Progress
8
Delayed
Legend Baseline Completed (on time) Completed (delayed) In Progress (on track) In Progress (delayed) Not Started
202520262027
PhaseBaselineActual
AprJulOctJanAprJulOctJanAprJul
StatusInvolved
Coordination
General
6 Jan 202531 Jan 20256 Jan 2025 → 31 Jan 2025
Completed
Andriani
CDA 1
Design
13 Jan 202528 Feb 202513 Jan 2025 → 7 Mar 2025
Completed
Rina
CDA 2
Design
1 Mar 202515 Apr 202510 Mar 2025 → 30 Apr 2025
Completed
Rina
SDA
Design
16 Apr 202530 Jun 20255 May 2025 → 20 Jul 2025
Completed
Rina
DD
Design
1 Jul 202531 Aug 202521 Jul 2025 → 30 Sep 2025
Completed
Rina
CD
Design
1 Sep 202531 Oct 20251 Oct 2025 → 30 Nov 2025
Completed
Rina
Tender
Procurement
1 Nov 202515 Dec 20251 Dec 2025 → 20 Jan 2026
Completed
Shop Drawing Review
Construction
16 Dec 202528 Feb 202621 Jan 2026 → 31 Mar 2026
Completed
Site Visit
Construction
1 Jan 202630 Jun 20271 Feb 2026 → ongoing
In Progress
CA
Construction
1 Feb 20261 Mar 202615 Feb 2026 → ongoing
Delayed
Rina